| Province | Subbasin | % |
|---|---|---|
| Columbia Plateau | John Day | 100.00% |
| Previous: | Next: |
|---|---|
| 74313 REL 108: 1993-066-00 EXP OREGON FISH SCREENS PROJECTS - IMPLEMENTATION |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Effective implementation management and timely contract administration | A: 119. Routine Administration of BPA Contract | 12/31/2023 | 12/14/2023 | |
| Complete Environmental Clearance Documentation or Prepare Biological Assessment | B: 165. Complete Environmental Clearance Documentation | 12/31/2023 | 12/14/2023 | |
| Develop or update (out-year) prioritized Habitat Project list: upload to Pisces | C: 114. Identify and prioritize new projects for future funding. | 12/31/2023 | 12/14/2023 | |
| Watershed Coordination Complete | D: 191. Design/Project coordination for specific projects. | 12/31/2023 | 12/14/2023 | |
| Projects installed. | H: 208. Wiwaanyatt Creek (Middle Fork John Day River) Project | 12/31/2023 | ||
| Projects installed. | I: 208. Parrish Creek #1 Project | 12/31/2023 | 12/14/2023 | |
| Projects installed. | J: 208. Parrish Creek #2 Project | 12/31/2023 | 12/14/2023 | |
| Projects installed. | K: 208. Buckhorn Creek Project | 12/31/2023 | ||
| Projects installed. | L: 208. Goose Creek #2 Project | 12/31/2023 | ||
| Projects installed. | M: 208. Paul Creek Project | 12/31/2023 | 12/14/2023 | |
| Pump fish screens and water measuring devices installed | Q: 208. Install Pump Fish Screens in the North Fork John Day River Drainage. | 12/31/2023 | 12/14/2023 | |
| Pump fish screens and water measuring devices installed | R: 208. Install Pump Fish Screens in the South Fork of the John Day River Basin. | 12/31/2023 | 12/14/2023 | |
| Pump fish screens and water measuring devices installed | S: 208. Install Pump Fish Screens in the Upper Mainstem John Day River Basin. | 12/31/2023 | 12/14/2023 | |
| Pump fish screens and water measuring devices installed | T: 208. Install Pump Fish Screens in the Umatilla River Basin. | 12/31/2023 | 12/14/2023 | |
| Aquatic and floodplain complexity improved | U: 29. Improve instream habitat in Murderers Creek | 12/31/2023 | 12/14/2023 | |
| Projects installed (no ground disturbance). | W: 186. Screen Component Replacement on oldest Screens; Install water control devices (South Fork John Day) | 12/31/2023 | 12/14/2023 | |
| Projects installed (no ground disturbance). | X: 186. Screen Component Replacement on oldest Screens; Install water control devices (Middle Fork John Day) | 12/31/2023 | 12/14/2023 | |
| Projects installed (no ground disturbance). | AA: 186. Screen Component Replacement on oldest Screens; Install water control devices (Umatilla River) | 12/31/2023 | ||
| Completed Annual Report | AH: 132. Submit Progress Report for the period 1/1/2022 - 12/31/2022 | 07/26/2023 | 07/26/2023 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 119 | Routine Administration of BPA Contract | |||||||
| B | 165 | Complete Environmental Clearance Documentation | |||||||
| C | 114 | Identify and prioritize new projects for future funding. | |||||||
| D | 191 | Design/Project coordination for specific projects. | |||||||
| E | 208 | Install Fish Exclusion Barriers on the Enterprise Ditch on the John Day River. | |||||||
| F | 208 | Install Fish Exclusion Barriers on the Enterprise Ditch on the John Day River. | |||||||
| G | 208 | Pine Creek (Anderson) Project | 04/09/2024 | ||||||
| H | 208 | Wiwaanyatt Creek (Middle Fork John Day River) Project | |||||||
| I | 208 | Parrish Creek #1 Project | 09/21/2023 | ||||||
| J | 208 | Parrish Creek #2 Project | 09/21/2023 | ||||||
| K | 208 | Buckhorn Creek Project | |||||||
| L | 208 | Goose Creek #2 Project | |||||||
| M | 208 | Paul Creek Project | 09/21/2023 | ||||||
| N | 208 | North Fork Walla Walla River #4 Project | 03/18/2024 | ||||||
| O | 208 | Install Pump Fish Screens in the Middle Fork of the John Day River Basin. | 03/29/2023 | ||||||
| P | 208 | Install Pump Fish Screens the Lower Mainstem John Day River Basin (downstream of the North Fork confluence). | 03/29/2023 | ||||||
| Q | 208 | Install Pump Fish Screens in the North Fork John Day River Drainage. | 03/29/2023 | ||||||
| R | 208 | Install Pump Fish Screens in the South Fork of the John Day River Basin. | 03/29/2023 | ||||||
| S | 208 | Install Pump Fish Screens in the Upper Mainstem John Day River Basin. | 03/29/2023 | ||||||
| T | 208 | Install Pump Fish Screens in the Umatilla River Basin. | 03/29/2023 | ||||||
| U | 29 | Improve instream habitat in Murderers Creek | 05/23/2023 | ||||||
| V | 186 | Screen Component Replacement on oldest Screens; Install water control devices (Lower John Day) | 03/29/2023 | ||||||
| W | 186 | Screen Component Replacement on oldest Screens; Install water control devices (South Fork John Day) | 03/29/2023 | ||||||
| X | 186 | Screen Component Replacement on oldest Screens; Install water control devices (Middle Fork John Day) | 03/29/2023 | ||||||
| Y | 186 | Screen Component Replacement on oldest Screens; Install water control devices (North Fork John Day) | 03/29/2023 | ||||||
| Z | 186 | Screen Component Replacement on oldest Screens; Install water control devices (Upper John Day) | 03/29/2023 | ||||||
| AA | 186 | Screen Component Replacement on oldest Screens; Install water control devices (Umatilla River) | 03/29/2023 | ||||||
| AB | 208 | Fields Creek #2 Headgate | |||||||
| AC | 208 | Fields Creek #3 Headgate | |||||||
| AD | 208 | Fields Creek #4 Headgate | 10/03/2022 | ||||||
| AE | 208 | Fields Creek #8 Headgate | 10/03/2022 | ||||||
| AF | 208 | Fields Creek #9 Headgate | 10/03/2022 | ||||||
| AG | 185 | Periodic Status Reports for BPA | |||||||
| AH | 132 | Submit Progress Report for the period 1/1/2022 - 12/31/2022 |